Work and rate practice

Work problems are about rates: how much of a job is done per hour. Rates add up; times don't.

0 of 70 done

Choose the correct answer

19 workers build a wall in 18 days. How many days would 18 workers take, working at the same rate?

Pick an answer

The first 10 questions of each category are free.

Tips for Work and rate

  • If a job takes 6 hours, the rate is 1/6 of the job per hour.
  • Working together: add the rates, then take the inverse to get the time.
  • Pipes that empty a tank have a negative rate.
Word Problems: Ages, Work Rate, Speed and Clocks

Worked examples: Work and rate

Three solved questions of this type. Try each one first, then read the answer and how to get it.

Example 1

Choose the correct answer

19 workers build a wall in 15 days. How many days would 5 workers take, working at the same rate?

Correct answer: C

How to solve it

Workers and days are inversely proportional: more workers, fewer days. The total work is 19 × 15 = 285 worker-days. With 5 workers: 285 ÷ 5 = 57 days.

Example 2

Choose the correct answer

24 workers build a wall in 40 days. How many days would 2 workers take, working at the same rate?

Correct answer: C

How to solve it

Workers and days are inversely proportional: more workers, fewer days. The total work is 24 × 40 = 960 worker-days. With 2 workers: 960 ÷ 2 = 480 days.

Example 3

Choose the correct answer

9 workers build a wall in 14 days. How many days would 21 workers take, working at the same rate?

Correct answer: C

How to solve it

Workers and days are inversely proportional: more workers, fewer days. The total work is 9 × 14 = 126 worker-days. With 21 workers: 126 ÷ 21 = 6 days.